Joint go-live critical path, both modules. Click any dot, label or table date to change it - the landing date recalculates instantly. Purple * = your edit, saved in this browser only. Baseline agreed 11 Aug 2026.
Journey
Milestones & What-if
Reading it: dot color = area. The journey flows left to right through the phase arrows; dots with a red glow are driving the go-live date; milestone status lives in the table below.
Go-live = the latest milestone plus the cutover buffer; the hardening phase (war rooms, runbook, prerequisites) sits between final sign-offs and go-live.
FAHR full integration stays TBD and is not on the go-live path - the workaround covers it.